Louisville

STATUS

 
end of page

“Shields” Plaques for Kill Devil.

Ceiling Tiles

in age paint process

95%
Deliver 3/18
75%
Deliver 3/18

Doors

Sealed. In paint now

75%
Deliver 3/25
Kill Devil

Casing in production

Hardware Received

Back Bar

not started. Easy to fabricate. begin construction Monday

0%
Deliver 4/5

Material in house

Red Boxes

constructed and ready for Red Gel coating, sanding and coating again

60%
Deliver 4/10
Marquee

VIP back lit

Box under construction

50%

Plastic in house ready to apply amber color

Deliver 4/5

plug and play

Pattern Cut

too yellow

too Dark

Frames

Molding in fabrication

30%

spandex purchased

Deliver 4/5

Lights purchased

this sample profile chosen

Column LED molding

Lights purchased

0%
Deliver 4/5

not begun

STILL LOOKING FOR BUMPER / GRILL FOR TENGO